MoSE, 210 million Euro more required. Completion delayed until 2020.
The completion date of the work slips, the costs rise: the Commissioners outline the new timetable By Alberto Zorzi VENEZIA: Five billion and 493 million Euro will not be enough. Not even six months remain from today to meet the deadline for the completion of work, which was set for 31 December 2018. Now comes … More MoSE, 210 million Euro more required. Completion delayed until 2020.